Date published: 30 January 2019 09:50
Modified On: 30 January 2019 10:00

New Lawsuit Against İzdemir Power Plant: 'There is Open Resistance Against Court Ruling’

Civil society organizations in İzmir have filed a lawsuit against the third positive Environmental Impact Assessment Report given for the İzdemir Power Plant to be built in Aliağa and Foça after the first two positive reports were cancelled by the court.
New Lawsuit Against İzdemir Power Plant: 'There is Open Resistance Against Court Ruling’
https://bianet.org/haber/new-lawsuit-against-izdemir-power-plant-there-is-open-resistance-against-court-ruling-204983
2024-05-20 22:25:33